现代防御技术 ›› 2024, Vol. 52 ›› Issue (5): 147-155.DOI: 10.3969/j.issn.1009-086x.2024.05.016

• 综合保障性技术 • 上一篇    

基于双层规划的装备保障优化预调度

胡志刚1, 楼京俊2, 史跃东2   

  1. 1.海军工程大学 管理工程与装备经济系,湖北 武汉 430033
    2.海军工程大学 舰船与海洋学院,湖北 武汉 430033
  • 收稿日期:2023-04-28 修回日期:2023-09-07 出版日期:2024-10-28 发布日期:2024-11-01
  • 作者简介:胡志刚(1983-),男,湖北蕲春人。讲师,博士,研究方向为装备保障、组合优化。
  • 基金资助:
    国家自然科学基金(41974005);海军工程大学自主立项项目(202250A060)

Optimal Prescheduling of Equipment Support Based on Two-Layer Programming

Zhigang HU1, Jingjun LOU2, Yuedong SHI2   

  1. 1.Department of Management Engineering and Equipment Economics,Navy University of Engineering,Wuhan 430033,China
    2.College of Naval Architecture and Ocean,Naval University of Engineering,Wuhan 430033,China
  • Received:2023-04-28 Revised:2023-09-07 Online:2024-10-28 Published:2024-11-01

摘要:

装备保障影响作战任务完成质量甚至直接关系任务成败,装备保障优化调度是提升装备保障系统效益的关键。针对装备保障系统双层决策和组合优化的特点,提出一种基于双层规划的装备保障优化预调度模型。分析装备保障系统运行过程和建模框架;结合组合优化问题,建立双层规划模型,上层为粗粒度层,采用MTSP(multiple travelling salesman problem)方法,下层为细粒度层,采用JSP(job-shop scheduling problem)方法;通过改进MTSP算法设计和迁移JSP算法描述构建双层迭代算法进行模型求解。算例分析表明:该方法在大规模系统优化调度中具有结构开放性和参数适应性。

关键词: 装备保障, 双层规划, 预调度, 大规模优化调度, 改进MTSP

Abstract:

Equipment support affects the completion quality of combat missions and even directly affects the success or failure of missions. Optimized scheduling of equipment support is the key to improve the efficiency of equipment support system. Aiming at the characteristics of two-layer decision making and combinatorial optimization of equipment support system, an optimized pre-scheduling model for equipment support based on two-layer programming is proposed. The operation process and modeling framework of the equipment support system are analyzed. Combining with the combinatorial optimization problem, a two-layer programming model is established. The upper layer is a coarse-grained layer, using the MTSP method and the lower layer is a fine-grained layer, using the JSP method. An example analysis shows that the proposed method has open structure and adaptive parameters in large-scale system scheduling optimization.

Key words: equipment support, two-layer planning, pre-scheduling, Large scale optimization scheduling, improving multiple travelling salesman problem(MTSP)

中图分类号: